Longfellow High School Fire Protection Sprinkler System Upgrade

ANTH

There are no resources or collections to display

Longfellow High School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive e-alerts or use the bell icon next to Project Updates to subscribe.

3017 E 31st St.
Minneapolis
MN
55406
612-668-4700

Scope of Work

Building wide replacement of the fire protection sprinkler system.

Project Updates

September- 

  • Fire sprinkler system upgrade project is complete.

August- 

  • Sprinkler system work scheduled for completion on or before August 15th.

July-

  • Replacement of sprinkler system in process.  Work to be completed in August.

June-

  • No new updates.

May-

  • Pre-construction planning in process – summer upgrade of the fire sprinkler system.

April-

  • Construction Results Corporation is under contract to perform the fire sprinkler upgrade.
  • Contractor is reviewing the site and preparing for summer construction.

March-

  • Contract with Construction Results Corporation is on the consent agenda for the March Board meeting.

February- 

  • Construction Results Corporation was awarded the contract for the fire sprinkler upgrade.
  • Contract will be on the March Board Consent Agenda
  • Construction – summer break 2024.

January - 

  • Bid documents have been issued and the project is in bidding.
  • Bids opened January 25, 2024
  • Contract to March Board meeting
  • Construction – summer 2024

December: New project added

Contact Us

Don Bielinski, Jr., Project Manager

Phone: 612-668-0700

Email: Donald.Bielinskijr@mpls.k12.mn.us

 

Project Schedule*

Design: Fall 2023
Bid Opening: TBD
Construction Start: June 2024
Substantial Completion: Mid-August 2024

Design Consultant: KFI Engineers

General Contractor: TBD

 