Andersen United Middle School Skylights
Anderson Middle School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.
Scope of Work
The project includes replacement of skylights damaged by hail in 2023. The skylights will be replaced with other transparent solutions to allow natural light into the school. The project will also include replacement of electrical components for building reliability.
Project Schedule*
Schematic Design Report: December 31, 2024
Design Development Report: January 2025
Cost Estimate #3: January 31, 2025
Construction Documents Report: February 7, 2025
Receive bids: March 6, 2025
BOE Construction Contract Approval: April 8, 2025
Pre-Construction Activities: April 2025
Construction start: Spring 2025
Construction substantial completion: August 29, 2025
Warranty period ends (one year): September 1, 2026
Architect: Wold Architects