2023

2023

December 2023: 

    1. Pre-construction meeting was held end of November with AVM Construction.
    2. Construction planning in process to commence construction during winter break.

November 2023: 

    1. General Contractor: AVM Construction
    2. Chiller construction to commence Winter Break through March 2024.
    3. Replacement of roofing at chiller location scheduled for summer break 2024.

October 2023: 

  1. Contract for chiller replacement tracking for the November MPS Board Consent Agenda.

September 2023: 

  1. Construction documents are published and the project is advertised for bidding.
  2. Pre-bid meeting scheduled for September 14, 2023
  3. Bids opened October 5, 2023
  4. November 14, 2023 for MPS Board Approval
  5. Phase 1: Chiller replacement – winter 2023/2024
  6. Phase 2: Replace section of roofing at chiller elevation summer 2024

August 2023: 

New chiller has been ordered and scheduled for delivery January 2024