2023
2023
December 2023:
-
- Pre-construction meeting was held end of November with AVM Construction.
- Construction planning in process to commence construction during winter break.
November 2023:
-
- General Contractor: AVM Construction
- Chiller construction to commence Winter Break through March 2024.
- Replacement of roofing at chiller location scheduled for summer break 2024.
October 2023:
- Contract for chiller replacement tracking for the November MPS Board Consent Agenda.
September 2023:
- Construction documents are published and the project is advertised for bidding.
- Pre-bid meeting scheduled for September 14, 2023
- Bids opened October 5, 2023
- November 14, 2023 for MPS Board Approval
- Phase 1: Chiller replacement – winter 2023/2024
- Phase 2: Replace section of roofing at chiller elevation summer 2024
August 2023:
New chiller has been ordered and scheduled for delivery January 2024