2024
2024
August-
- Roofing work complete.
July-
- Roofing work in process – to be completed by end of July.
June-
- No new updates.
May-
- Reroof the deck surface where the new chiller was installed.
April-
- No new updates.
March-
- Chiller has been installed.
- Chiller electrical work is in process.
- Chiller piping connections are in process.
- Factory chiller start-up scheduled week of April 1st – 5th.
February-
- Electrical prep work continues for the new chiller.
- New chiller scheduled to be placed on Barton roof – March 1, 2024
- New chiller start-up April 1st – 5th, 2024
- Reroof deck at the chiller location – summer break 2024
January-
- Over winter break, the old chiller was removed from the roof of the school, and the new chiller platform was constructed on the roof. Select mechanical and electrical demolition was performed in preparation for the new chiller.
- Electrical and mechanical work, for the new chiller, will continue through January and February.
- Crane new chiller to Barton roof – tentative for March 1, 2024
- Factory start-up for new chiller – spring break