2023
2023
December 2023:
- CLOSE OUT/WARRANTY
- Rebates
- Closeout submittals from Shaw Lundquist
- Final payment
October 2023:
- CLOSE OUT PENDING FINAL PAYMENT. Final Update, no more requests.
September 2023:
- Final walk through and 11 Month warranty walk through completed on 30Aug23.
- Minor issues for Shaw Lundquist to correct.
- Project in Closeout/Warranty at this point w/ ACTION for Shaw Lundquist.
- Re-Training for AV PENDING.
- Shaw should be complete and closed out by end of September.
August 2023:
- Designer: WOLD Contractor: Shaw Lundquist
- Project In Punchlist/Closeout/Warranty
- Addressing outstanding Punchlist & Warranty items
- Awaiting Contractor Closeout items.
- Expect full contract closeout by beginning of school.
June 2023:
- Project in punchlist/closeout.
- Performance (Theater) is being used by Bethune
- Expect closeout final payment in late June 2023
April 2023: 98% complete. All supply chain items have been delivered. Theatrical Sub., completing AV & Lighting controls. Once complete, Wold/APF will Commission Performance. Then final clean and it will be turned over to the school. Expected turnover date – 1st week in May.
March 2023: There are no updates at this time.
February 2023: We are accepting a Value Engineering (VE) solution such that the performance addition will be complete and ready for use in early April.
January 2023:
- Majority of Performance Center Construction is complete.
- Supply Chain Delays:
- Cisco Network Switch (Specified)
- MPS IT Dept., has a switch that can used in the interim until the switch arrives
- Crestron Processor – Expected Delivery Aug 23
- AV System
- Theatrical Lighting System
- Cisco Network Switch (Specified)
- Grand Opening/Ribbon Cutting Ceremony
- Sometime in April or May 2023