December:
- Project in Closeout
November:
- Project in Closeout w/ MORCON (GC)
- Waiting on a signed contract from MPS w/ H2i to refinish the front of stage in Jan/Feb 25
October:
- Closeout phase.
September:
- Ella Baker is in punch list/closeout/Training phase.
July:
Morcon
Started in AUDITORIUM on 1May24
- Demo complete
- NAC & Gopher Stage Lighting are working on wiring and installation of stage equipment for the next few weeks.
- Floor Prep & Sealer will occur in the next week or so.
- New Seating to arrive end of July for install in early August.
Science Classrooms (302, 304 & 334):
- Abatement complete
- Demo existing millwork complete
- Demo Wall openings for plumbing
- Electrical Piping rough in occurring
- Core drilling for plumbing occurring
- New Cabinets/Casework to arrive end of July
Project on schedule and within allocated Budget.
May:
- Pending input from MPS Board
January:
- No new updates