2025
2025
September-
- Project Complete
- PEND Final pay for DLR Group and project will be closed and in warranty.
- Dan G – copied, can reallocate remaining $’s.
July-
- Final Closeout
- Final pay Morcon
- Final pay DLR Group
May-
- H2I: Front of stage refinishing completed
- Punchlist work to be completed 9Jun25 & beyond.
- Morcon
- Lights on back order arrived, installed & operating as intended.
- MPS will reject the Tarkett tile in Science Labs due to Morcon not prepping the floors in accordance with Manufactures guidelines.
- Floors look horrible for being new.
- Morcon in Project Closeout.
April-
- Some lights have been on back order since Sept 24
- Accepted an alternate fixture that should arrive in a couple weeks
- Morcon in closeout phase
- Refresher Training for Staff requested for 24Apr25
March:
- Project in Closeout
February:
- Project in Closeout
- Auditorium light on backorder and should arrive in 8 weeks.
January:
- Project in Closeout