2025

2025

September-

  • Project Complete
  • PEND Final pay for DLR Group and project will be closed and in warranty.
  • Dan G – copied, can reallocate remaining $’s.

July-

  • Final Closeout
  • Final pay Morcon
  • Final pay DLR Group

May-

  • H2I: Front of stage refinishing completed
    • Punchlist work to be completed 9Jun25 & beyond.
  • Morcon
    • Lights on back order arrived, installed & operating as intended.
    • MPS will reject the Tarkett tile in Science Labs due to Morcon not prepping the floors in accordance with Manufactures guidelines.
      • Floors look horrible for being new.
    • Morcon in Project Closeout.

April-

  • Some lights have been on back order since Sept 24
    • Accepted an alternate fixture that should arrive in a couple weeks
  • Morcon in closeout phase
  • Refresher Training for Staff requested for 24Apr25

March: 

  • Project in Closeout

February: 

  • Project in Closeout
  • Auditorium light on backorder and should arrive in 8 weeks.

January: 

  • Project in Closeout