2023
2023
December 2023:
- TAB in process
- Commissioning in process
September 2023:
- Punchlist
- ERU’s – PEND Start up, TAB & Commissioning
- Close out
September 2023:
- Shaw Lundquist substantially complete on 1Sept23.
- There is some spill over Energy Recovery Unit work on the roof that will go until late September.
- There is some electrical lighting and ceiling work that is ongoing.
- Punchlist work occurring during the day in non-public area.
- Shaw Lundquist should be complete by Mid-October.
August 2023:
- Designer: LHB Contractor: Shaw Lundquist
- Shaw Lundquist in Demo mode
- Work progressing according to schedule
- Currently see no issues that should affect school opening.
June 2023:
- Project in Pre-Construction Phase
- Shaw Lundquist is starting early in the Kitchen w/ barrier walls separating the construction from the public
- Staff/Principal “in the loop” as far as school expectations & preparation for summer construction
- Staff is coordinated with for move out/in activities and Asbestos abatement
April 2023: Going through pre-construction shops/submittals and pre-mob activities.
March 2023: Preconstruction activities are ongoing. Construction is expected to begin in June 2023.
February 2023: Preconstruction activities are underway. Construction is expected to begin in June 2023.
Januart 2023: We will begin pre-construction activities soon. Construction is expected to begin in June 2023.