2023

2023

December 2023:

  • TAB in process
  • Commissioning in process

September 2023:

  • Punchlist
  • ERU’s – PEND Start up, TAB & Commissioning
  • Close out

September 2023:

  • Shaw Lundquist substantially complete on 1Sept23.
  • There is some spill over Energy Recovery Unit work on the roof that will go until late September.
  • There is some electrical lighting and ceiling work that is ongoing.
  • Punchlist work occurring during the day in non-public area.
  • Shaw Lundquist should be complete by Mid-October.

August 2023:

  • Designer:  LHB   Contractor:  Shaw Lundquist
  • Shaw Lundquist in Demo mode
  • Work progressing according to schedule
  • Currently see no issues that should affect school opening.

June 2023:  

  • Project in Pre-Construction Phase
  • Shaw Lundquist is starting early in the Kitchen w/ barrier walls separating the construction from the public
  • Staff/Principal “in the loop” as far as school expectations & preparation for summer construction
  • Staff is coordinated with for move out/in activities and Asbestos abatement

April 2023:  Going through pre-construction shops/submittals and pre-mob activities.

March 2023:  Preconstruction activities are ongoing.  Construction is expected to begin in June 2023.

February 2023:  Preconstruction activities are underway.  Construction is expected to begin in June 2023.

Januart 2023:  We will begin pre-construction activities soon.  Construction is expected to begin in June 2023.