2026
2026
July-
Windows- Lintel work complete. Window installation and trim work continue.
April-
Working on pre-construction activities. Phase two work will begin in June 15th.
March-
Phase 2 of the project has been awarded to Construction Results Corp. In pre-construction activities now.
February-
We are bidding Phase 2 of this project. This includes the remainder of lintel work and window installations.
- CURRENT PROJECT