2024
2024
December:
- Project in Closeout
November-
- Project in Closeout/Warranty
October-
- Closeout phase.
September-
- Currently in punch list/closeout phase.
July- MEP Upgrades:
- Abatement is the main push currently. Will complete Area #01 on 11Jul24.
- Master Mechanical will take possession of “yellow” on attached on 12Jul24.
- Project on Schedule and within allocated Budget.