2025

2025

December-

Click here to see the latest LSE Field Observation Report

Bid opening for Phase 2 held on December 16, 2026. No contract awarded as all bids received were over project budget. Revision of Phase 2 schedule and phasing underway.

November-

Click here to see the latest LSE Field Observation Report

October-

Click here to see the latest LSE’s Field Observation Reports

September-

  • CRC is doing Punchlist completion
  • Dust collector work to occur over MEA
    • Structural Steel

July-

  • Substantial Completion on 15Aug25
  • See attached LSE/Hallberg Field Observation Reports.

May-

  • Pre-Construction Conference set for 27May25.
  • CRC (Construction Results Corporation) set to Mobilize & Begin on 11Jun25.
  • Moving/Abatement to be coordinated with CRC.

April-

  • Construction Results won’t begin until around 12Jun25
  • We are in the pre-construction phase.  Submittals and etc., prior to construction.

March-

  • Construction Results
    • Contract start up
    • Submittals

February -

  • In Contract award phase.
  • Construction Results submitting “Notice of Award” and “Notice to Proceed” submittals.
  • Pre-Construction Conference to occur sometime in April or May.

January -

  • Awarded in BOE meeting. CTE Phase I:  Construction Results Corp