2025
2025
December-
Click here to see the latest LSE Field Observation Report
Bid opening for Phase 2 held on December 16, 2026. No contract awarded as all bids received were over project budget. Revision of Phase 2 schedule and phasing underway.
November-
Click here to see the latest LSE Field Observation Report
October-
Click here to see the latest LSE’s Field Observation Reports
September-
- CRC is doing Punchlist completion
- Dust collector work to occur over MEA
- Structural Steel
July-
- Substantial Completion on 15Aug25
- See attached LSE/Hallberg Field Observation Reports.
May-
- Pre-Construction Conference set for 27May25.
- CRC (Construction Results Corporation) set to Mobilize & Begin on 11Jun25.
- Moving/Abatement to be coordinated with CRC.
April-
- Construction Results won’t begin until around 12Jun25
- We are in the pre-construction phase. Submittals and etc., prior to construction.
March-
- Construction Results
- Contract start up
- Submittals
February -
- In Contract award phase.
- Construction Results submitting “Notice of Award” and “Notice to Proceed” submittals.
- Pre-Construction Conference to occur sometime in April or May.
January -
- Awarded in BOE meeting. CTE Phase I: Construction Results Corp