2026

2026

June-

The Board of Education approved Rochon Corporation’s construction contract for Phase 2 on June 9th, 2026.

July-

Preconstruction meeting held on July 8th, 2026.

Security fence installed. Interior demolition has started. Northeast parking lot has been striped. Excavation for footings for building addition to begin shortly.

May-

Bid opening for Phase 2 held on May 14th, 2026. LSE Architects recommends award of contract to Rochon Corporation contingent on Board of Education approval.

April-

Revised Phase 2 documents posted for bids on April 14th, 2026 (OP#26-2623)

Mandatory pre-bid meeting held on April 29th, 2026.

March-

Construction Results Corporation finalizing the installing of the construction lab dust collector sweeps and controls for Phase 1.

February-

Phase 1 owner trainings and close-out documents in progress.

January-

Substantial Completion signed January 16, 2026  for Phase 1 delayed work (Overhead door 1024B in Collision, dust collector system, completion of secure entry items, electrical punchlist items, mechanical insulation and identification, TAB and commissioning items).