2023

2023

December 2023:

    1. Installation of lights and lighting controls continues on second shift.

November 2023: 

    1. Installation of lights and lighting controls continues on second shift.

October 2023:

  1. Installation of lighting and lighting controls work continues on the second shift.

September 2023:

  1. Electrical contractor has moved to second shift – performing work each day after education hours.
  2. Work continues on the installation of lighting controls and new LED fixtures.

 

August 2023: (No changes from last month)

July 2023:

  1. Installation of new LED lighting and new lighting controls is underway.
  2. Current work is focused on updating outdated lighting controls during summer break.
  3. LED light fixture replacement has started in some areas.  Lighting replacement/upgrades will continue into the fall.  Installation will shift to evenings after staff and students return to school.

June 2023: Scheduled to begin work week of June 19th

May 2023: No updates at this time

March 2023: Contract awarded to NAC Mechanical and Electrical Services

January 2023: 

  • Pre-bid meeting January 24, 2023
  • Bids Opened February 7, 2023