  • Project is finished

November -

  • Construction being completed on upgrade to the fire sprinkler system in the bus garage.  Work is substantially complete.

October -

  • No new updates.

September-

  • Fire Sprinkler system upgrade work is underway in the Transportation bus garage.  Completion – November 2024.

August-

  • Replacement of the fire sprinkler system in the MPS Transportation bus garage began August 5th. Substantial completion of work is scheduled for mid-November.

July-

  • Fire Sprinkler pre-construction meeting on July 17th
  • Sprinkler replacement in the bus garage to begin August

June-

  • Contract on June 11th Board Consent Agenda.

May-

  • Contractor – Dynamic Fire Protection
  • Construction schedule: August 2024 – November 2024

April-

  • In bidding – bids due April 18, 2024

March-

  • 95% bid documents have been completed.
  • Project to advertise Mid- March 2024.
  • Bids opened April 18, 2024.
  • Construction summer/fall 2024

February -

  • Project to start in Summer/Fall 2024
  • CURRENT PROJECT