2024
2024
December -
- Project is finished
November -
- Construction being completed on upgrade to the fire sprinkler system in the bus garage. Work is substantially complete.
October -
- No new updates.
September-
- Fire Sprinkler system upgrade work is underway in the Transportation bus garage. Completion – November 2024.
August-
- Replacement of the fire sprinkler system in the MPS Transportation bus garage began August 5th. Substantial completion of work is scheduled for mid-November.
July-
- Fire Sprinkler pre-construction meeting on July 17th
- Sprinkler replacement in the bus garage to begin August
June-
- Contract on June 11th Board Consent Agenda.
May-
- Contractor – Dynamic Fire Protection
- Construction schedule: August 2024 – November 2024
April-
- In bidding – bids due April 18, 2024
March-
- 95% bid documents have been completed.
- Project to advertise Mid- March 2024.
- Bids opened April 18, 2024.
- Construction summer/fall 2024
February -
- Project to start in Summer/Fall 2024
- CURRENT PROJECT