Andersen United Middle School

Final

Andersen United Community School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive e-alerts 

1098 Andersen Lane
Minneapolis
MN
55407
612-668-4200

Scope of Work

Improvements at Andersen are proposed within a 5-Year plan. Work will be completed as funding is approved for each phase.

The CDD has designated this school to become a community middle school with a dual language magnet program. The facility has a 5-year plan for renovations.

Phase 1 work was completed in Summer 2021 and included updates to lighting in the stairwells, some new furniture, additional lockers, and reworking existing restrooms to be student single-user restrooms. This helped us to make the school more functional for the middle school students.

Phase 2 work included the creation of 8 science labs in existing classrooms, daylighting upgrades throughout the building, mechanical and finishes updates, the start of work on a centralized full-prep kitchen, and additional classroom furniture.

Phase 3 work will include the completion of the full-preparation kitchen space, creation of a central cafeteria/auditorium space adjacent to the new kitchen, and restroom updates.

Additional goals for our 5-year capital plan include improvements to technology spaces and general work required for maintenance and operation of the building. These future projects are not funded at this time.

A virtual community meeting was held on June 1, 2021 to provide information about the project, including the planning and design process and timeline. View the presentation here: Andersen Community Engagement Presentation.

We invited interested members of the community to be involved in the project as part of our Stakeholder Committee.

Project Updates

March - Phase 3 preconstruction planning has been scheduled. Construction is expected to begin in June 2023.

February- The Phase 3 construction contract was approved by the BOE and is in the process of being fully executed. Preconstruction work will begin soon.

January - Work on site is mostly complete. The canopy lighting will be completed this month as well as some additional punch list items. The Phase 3 construction contract will be on the BOE agenda for approval at the February 14, 2023 meeting.

Contact Us

Curt Hartog
Executive Director, Capital Planning, Construction, Maintenance and Operations
612-668-0274
curtis.hartog@mpls.k12.mn.us

Share Your Feedback

Share your questions about Andersen's upcoming improvement project.

Submit a Question

Frequently Asked Questions

Project Schedule*

Phase 3: Andersen United Middle School Renovations (Pending BOE approval)

  • Design: Spring/Summer 2022
  • Construction Start: June 2023
  • Substantial Completion: August 2023 / (Student-Occupied Areas) / November 2023
  • Architect: Wold Architects and Engineers
  • General Contractor: Construction Results Corporation

Phase 2: 2022 Andersen United Middle School Renovations

  • Design: Spring/Summer 2021
  • Construction Start: April 2022 (Limited Areas) / June 2022
  • Substantial Completion: Fall 2022 / Winter 2023
  • Architect: Wold Architects and Engineers
  • General Contractor: Construction Results Corporation

Phase 1: 2021 Andersen United Middle School Renovations

  • Substantial Completion: Summer 2021
  • Architect: Wold Architects and Engineers
  • General Contractor: PCL Construction

*Please note, all project schedules are subject to change.

Project Photos and Resources

Andersen United Middle School

12 22
12 22
12 22
01 23
12 22
12 22
Top of Page Render
10 22
OCT2022
OCT2022
OCT2022
SEPT22
SEPT22
SEPT22
SEPT22
July 22
July 22
July 22
July 22
Aug 22
Aug 22
Aug 22
Aug 22
June 22
11
July 22
9
Aug 22
01 23
8
SEPT22
7
6
22
5
4
3
2
1