December 2022: Architectural punchlist can be completed on the performance addition. We are close to also being able to both commission & complete the punchlist inspections for theatrical, electrical & mechanical. Next steps will be to complete owner training for theatrical.
November 2022: Construction – Performance Addition
October 2022:
- Interior Remodeling is complete except for the Kiln & AV for Gym/Band Rooms
- Plan is to complete a FINAL Punchlist Walk through on 25Oct22.
- Performance Center work is progressing and is contractually due on 30Dec22.
- Potential supply chain issues with ETC AV Controller for Performance Center.
September 2022:
Dance Room:
- Floor had to be leveled
- Due to curing, it took longer than expected.
- Working in the room right now and it should be completed by the week of the 19th.
Performance Addition:
- Shaw Lundquist is planning for turnover on Oct 31, 2022 but the contractual date was Dec 30, 2022. This is dependent on the seating arriving from Europe (Belgium) in a timely manner.
June 2022: Project is currently on track and there are no updates to report at this time.
May 1, 2022:
- Foundation work for the addition is nearly complete.
- Underground Plumbing work is starting
- Building steel and precast concrete frame will start being building this month
April 1, 2022: Shaw’s earthwork contractor – Kevitt, mobilized to site on Monday 4/4/22 and began clear & grub activities. Over the next few weeks, they will need to remove unsuitable soils from the site and get to grade where they will begin helical piles.
February 4, 2022:
- Pre-Construction Conference for Shaw Lundquist (General Contractor) scheduled for Tuesday – March 15, 2022 from 8:30 am to 10 am (Multi-Purpose/Lunchroom #124).
- Shaw Lundquist to begin Mobilization on April 01, 2022
- Shaw Lundquist to begin Foundation / Footing work sometime in April – after the frost is out.
- Interior renovations for the Arts Magnet will not begin until after school ends in Mid-June and the spaces moved out.
- Weekly Progress Meetings: 9 am to 10 am every Tuesday beginning on April 12, 2022 until end of October 2022.
January 4, 2022: Pre Construction Phase