Bryn Mawr HVAC Renovation 2026
Bryn Mawr Elementary School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.
Scope of Work
The project scope continues to be refined within budget. The overall goal is to renew the most critical electrical and mechanical assets which are crucial to HVAC reliability and performance. Depending on budget availability, scope of work may include the renewal or replacement of the electrical and mechanical equipment such as eighteen (18) unit ventilators, six (6) air handling units, one (1) make up air unit, eleven (11) vav’s, thirteen (13) unit heaters, four (4) return/relief fans and seven (7) exhaust fans, associated connections, fittings and any incidentals necessary to successfully complete and commission within budget and schedule.
Contact Us
Grant Lindberg , Project Manager
Phone: 612-668-0281
Email: Grant.Lindberg.mpls.k12.mn.us
Project Schedule*
Project Schedule: Construction Renovation, Summer 2027
Design: Spring 2026
Consultant: Widseth
General Contractor: TBD
Architect: Widseth
Substantial Completion: August 2027
Bid Documents to be Issued: August 2026
Mandatory Pre-bid Meeting: August 2026
Bid Due Date: August 2026
MPS Formal School Board Approval: September 2026
Construction early start: June 2027
Last day of school: June 2027
Substantial completion: August 2027
Final Completion: August 2027
First day of school: 30 August 2027 TBD