Skip To Main Content

Select a School

Playground Site Updates

 

Scope of Work

The schools listed below are scheduled to undergo a playground replacements.

Anishinabe Academy/Sullivan:  Fall 2026 

  • Work
    • Playground renewal, equipment and surface 
    • Vendor - Flagship
    • PM - Lyssa Washington
    • Cost: $200,000
      • Waiting on Images

Bryn Mawr:  COMPLETED

  • Work
    • Playground renewal, equipment and surface 
    • Flagship
    • PM - Mauricio Ochoa
    • Cost: $300,000
      • Images available below

Ella Baker:  COMPLETED

  • Work
    • Renew play equipment, surface and fencing
    • Kompan
    • PM - Mauricio Ochoa
    • Cost: $300,000
      • Images available below

Cooper: COMPLETED

Work 

  • Playground renewal - equipment, surface, & repairs
    • Kompan
    • PM: Mauricio Ochoa
    • $100,000
      • Images available below

Hale: COMPLETED

Work 

  • Playground renewal - equipment, surface, & repairs
    • Flagship
    • PM: Mauricio Ochoa
    • $150,000
      • Images available soon

Kenwood:  COMPLETED

  • Work
    • Playground equipment and surface renewal
    • Kompan
    • PM - Ann Cerney
    • Cost: $300,000
    • Installation: Tentatively scheduled for beginning of October, 2024
      • Images available below

Longfellow:

  • Work
    • Remove play equipment in courtyard
    • TBD
    • PM - Geye
    • Cost: $30,000

Lyndale:  Will be completed by 10/30/2026

  • Work
    • Playground renewal, equipment and surface 
    • Vendor - Flagship
    • PM - Lyssa Washington
    • Cost: $300,000
      • Images available soon

Northrop - Ericsson: Completed

  • Work
    • Playground renewal, swing equipment and surface 
    • MN/WI
    • PM - Ann Cerney
    • Cost: $100,000
      • Images available below

North Star:

  • Work
    • Playground set removal, clear and restore grade
    • Vendor TBD
    • PM - Ann Cerney
    • Cost: $30,000

Pillsbury:  COMPLETED

  • Work
    • Playground renewal, equipment and surface 
    • Vendor - Flagship
    • PM - Lyssa Washington
    • Cost: $200,000
      • Images available below

Pratt: COMPLETED

  • Work
    • Playground renewal, equipment and surface 
    • Flagship
    • PM - Mauricio Ochoa
    • Cost: $200,000
      • Images available below

Wenonah: 

  • Work
    • Playground Refresh - remove metal pipes & timbers & remove sand - Tot Lot remove monkey bars - add Special Ed Equipment, remove sand
    • TBD
    • PM - Lee Setter
    • Cost: $115,000

Images

Playground Projects

Children play on a colorful playground set with woodchips in the foreground, set against a backdrop of lush green trees and a blue sky.
A colorful children's playground with various climbing structures and swings sits in the foreground against a backdrop of dense green trees under a blue sky.
A yellow and blue children's playground structure stands on a white surface against a solid black background.
A yellow and blue modular playground set stands against a plain white background.
A swing set stands on a snow-dusted playground in the foreground, with a large brick building and bare trees under a clear blue sky in the background.
Ella Baker Option B
A blue playground set with swings and climbing equipment sits on a sandy area surrounded by a green lawn and leafy trees.
A colorful, inclusive playground with various climbing structures and swings is filled with children on a sandy surface against a plain white background.
A green and grey playground set with swings and a slide sits on a sandy area surrounded by green grass and leafy trees.
A colorful children's playground with slides and climbing structures sits on wood chips and rubber matting, set against a backdrop of green trees and a clear blue sky.

Contact Us

Lyssa Washington, Project Manager

Phone: 612-978-9361

Email: Lyssa.Washington@mpls.k12.mn.us