Current School Playground Site Updates
Scope of Work
The schools listed below are scheduled to undergo a playground replacements.
Anishinabe Academy/Sullivan: 2026
- Work
- Playground renewal, equipment and surface
- Vendor TBD
- PM - Mauricio Ochoa
- Cost: $200,000
- Waiting on Images
Bryn Mawr: COMPLETED
- Work
- Playground renewal, equipment and surface
- Flagship
- PM - Mauricio Ochoa
- Cost: $300,000
- Images available below
Ella Baker: COMPLETED
- Work
- Renew play equipment, surface and fencing
- Kompan
- PM - Mauricio Ochoa
- Cost: $300,000
- Images available below
Cooper: COMPLETED
Work
- Playground renewal - equipment, surface, & repairs
- Kompan
- PM: Mauricio Ochoa
- $100,000
- Images available below
Hale: COMPLETED
Work
- Playground renewal - equipment, surface, & repairs
- Flagship
- PM: Mauricio Ochoa
- $150,000
- Images available soon
Kenwood: COMPLETED
- Work
- Playground equipment and surface renewal
- Kompan
- PM - Ann Cerney
- Cost: $300,000
- Installation: Tentatively scheduled for beginning of October, 2024
- Images available below
Longfellow:
- Work
- Remove play equipment in courtyard
- TBD
- PM - Geye
- Cost: $30,000
Lyndale: 2026
- Work
- Playground renewal, equipment and surface
- Vendor TBD
- PM - Mauricio Ochoa
- Cost: $300,000
- Waiting on Images
Northrop - Ericsson: Completed
- Work
- Playground renewal, swing equipment and surface
- MN/WI
- PM - Ann Cerney
- Cost: $100,000
- Images available below
North Star:
- Work
- Playground set removal, clear and restore grade
- Vendor TBD
- PM - Ann Cerney
- Cost: $30,000
Pillsbury: 2026
- Work
- Playground renewal, equipment and surface
- Vendor TBD
- PM - Mauricio Ochoa
- Cost: $200,000
- Waiting on Images
Pratt: COMPLETED
- Work
- Playground renewal, equipment and surface
- Flagship
- PM - Mauricio Ochoa
- Cost: $200,000
- Images available below
Wenonah:
- Work
- Playground Refresh - remove metal pipes & timbers & remove sand - Tot Lot remove monkey bars - add Special Ed Equipment, remove sand
- TBD
- PM - Lee Setter
- Cost: $115,000
Images
Contact List
Mauricio Ochoa, Project Manager
Phone: 612-559-2574
Email: Mauricio.Ochoa@mpls.k12.mn.us
Ann Cerney, Project Manager
Phone: 612-668-0013
Email: Ann.Cerney@mpls.k12.mn.us
Diedra Geye, Project Manager
Phone: 612-668-0055
Email: Diedra.Geye@mpls.k12.mn.us