Renovation of the Dowling Elementary School gymnasium including floor refinishing, painting, acoustic wall panels, replacement of divider curtain, hoops & equipment, safety wall mats, audio visual equipment and addition of scoreboards. Project is receiving grant funding through the Hennepin County Youth Activities Grants Program.
Contact Us
Julia Kastelberger, Project Manager
Phone: 612-461-3732
Email: julia.kastelberger@mpls.k12.mn.us
Project Schedule*
Design: January- February 2026
Architect: Wendel Architecture, PC
General Contractor: TBD
Bid Documents to be Issued: February 27, 2026
Mandatory Pre-bid Meeting: March 13, 2026
Bid Due Date: March 20, 2026
MPS Formal School Board Approval: April 14, 2026
Pre-Construction: May 2026
Last day of school: June 10, 2026
Construction start: June 11, 2026
Substantial completion: August 28, 2026
First Day of School: September 8, 2026
Final Completion: September 25, 2026