Dowling Elementary School Gymnasium Renovation

Dowling Elementary School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Renovation of the Dowling Elementary School gymnasium including floor refinishing, painting, acoustic wall panels, replacement of divider curtain, hoops & equipment, safety wall mats, audio visual equipment and addition of scoreboards. Project is receiving grant funding through the Hennepin County Youth Activities Grants Program.

3900 W River Pkwy.
Minneapolis
MN
55406
612-668-4410

Project Updates

February-

Call for Bids (OP #26-2620) posted on February 27, 2026.

January-

Wendel Architecture, PC awarded design contract.

 

Contact Us

Julia Kastelberger, Project Manager

Phone: 612-461-3732

Email: julia.kastelberger@mpls.k12.mn.us

 

Project Schedule*

Design: January- February 2026

Architect:  Wendel Architecture, PC

General Contractor: TBD

Bid Documents to be Issued:  February 27, 2026

Mandatory Pre-bid Meeting:  March 13, 2026

Bid Due Date: March 20, 2026

MPS Formal School Board Approval: April 14, 2026

Pre-Construction: May 2026

Last day of school:  June 10, 2026

Construction start:  June 11, 2026

Substantial completion:  August 28, 2026

First Day of School:  September 8, 2026

Final Completion:  September 25, 2026

Project Photos and Resources

Dowling Elementary School Gymnasium Renovation

The image depicts a simple diagram with various shapes and symbols arranged horizontally, representing some kind of information or data.
The image appears to be a technical drawing or schematic, depicting a rectangular structure with two windows and various grid lines and annotations.