Edison High School CTE
Edison High School is scheduled to undergo a CTE renovation as outlined below. To receive periodic updates on project milestones and other news, please sign up to receive e-alerts.
Scope of Work
A new CTE center will be constructed on the south side of Edison High School in the former shops’ areas. The project includes a new agriculture area and new classrooms and office areas to support CTE at Edison. Additional improvements are being made to support the DCD program including updated classrooms and bathroom facilities.
Contact Us
Jeff Helstrom, Project Manager
Phone: 612-668-0305
Email: Jeffrey.Helstrom@mpls.k12.mn.us
Project Schedule*
Design: LSE Architects – Design Completed October 14th 2024
Construction: March 3rd 2025 to August 15th 2025
General Contractor: Jorgenson Construction Inc.
Architect: LSE Architects
Substantial Completion: August 15th, 2025
Bid Documents to be Issued: October 2024
Mandatory Pre-bid Meeting: October 17th 2024
Bid Due Date: November 7th 2024
MPS Formal School Board Approval: January 14th 2025
Construction early start: March 3rd 2025
Last day of school: June 6th 2025
Substantial completion: August 15th 2025
Final Completion: November 2025
First day of school: September 2nd 2025