Edison High School CTE

Edison High School is scheduled to undergo a CTE renovation as outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive e-alerts.

Scope of Work

A new CTE center will be constructed on the south side of Edison High School in the former shops’ areas. The project includes a new agriculture area and new classrooms and office areas to support CTE at Edison. Additional improvements are being made to support the DCD program including updated classrooms and bathroom facilities.

700 22nd Ave. NE
Minneapolis
MN
55418
612-668-1300

Project Updates

September-

  • JCI is doing Punchlist completion
  • JCI is in the process of finishing up incomplete work in classrooms & ag lab
  • Click here to see the latest LSE’s Field Observation Reports

July -

  • Substantial Completion on 15Aug25
  • See attached LSE/Hallberg Field Observation Reports.

May -

  • JCI (Jorgenson Construction Inc) doing non-disruptive work during school days.

April -

  • Jorgenson Construction Inc. (JCI) has mob’d to site and begun “non-disruptive” work during school hours.
  • We’ve Id’d some CODE issues that need to be resolved via Change Order.
  • JCI on schedule and no budgetary issues at this point.

March -

  • JCI – Jorgenson Construction Inc., has mobilized and is doing non-disruptive work during the day’s until Summer 2025.
  • Submittal Processing
  • RFI Processing

February -

  • Had the Pre-Con yesterday
  • Jorgenson Construction Inc., is waiting on Permit from City of MPLS.
  • Planned start is 5Mar25 allowing some days for move out.
    • JCI will complete non-disruptive work during the school day
    • Saw cutting will occur prior to or after school
  • JCI is in the mobilization/start up mode.

January -

  • Awarded in BOE meeting.
  • Edison CTE:  Jorgenson Construction Inc. (JCI)

October -

  • Design Completed October 14th 2024

Contact Us

Jeff Helstrom, Project Manager

Phone: 612-668-0305

Email: Jeffrey.Helstrom@mpls.k12.mn.us

Project Schedule*

Design:   LSE Architects – Design Completed October 14th 2024

Construction:  March 3rd 2025 to August 15th 2025

General Contractor: Jorgenson Construction Inc.

Architect:  LSE Architects

Substantial Completion:  August 15th, 2025

Bid Documents to be Issued:  October 2024
Mandatory Pre-bid Meeting:  October 17th 2024
Bid Due Date:  November 7th 2024
MPS Formal School Board Approval:  January 14th 2025
Construction early start:  March 3rd 2025
Last day of school:  June 6th 2025
Substantial completion:  August 15th 2025
Final Completion:  November 2025
First day of school:  September 2nd 2025

 