Franklin Middle School Auditorium Sound & Light System Upgrades

Franklin Middle School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

1501 Aldrich Ave. N
Minneapolis
MN
55411
612-668-2600

Scope of Work

Franklin Middle School is scheduled to receive updates to their sound and light systems in the Auditorium.  

Project Updates

August- Project is being redesigned to rebid for Summer 2025

June- Project being re-bid

May- Project being re-bid

April- Project being re-bid

March- Project came in over budget and is being Re-Bid.

                

December - Project is in design phase with Schuler Shook. 

October: New Project

Contact Us

Ann Cerney, Project Manager

Phone: 612-685-3048

Email: Ann.Cerney@mpls.k12.mn.us

 

 

Project Schedule*

Construction: TBD

Project Schedule*

Design: Fall/Winter 2023

Construction: June 2024

General Contractor: TBD

Architect:  Schuler Shook

Substantial Completion: October 18, 2024

Bid Documents to be Issued:  January 9, 2024
Mandatory Pre-bid Meeting:  January 18, 2024
Bid Due Date:  February 13, 2024
MPS Formal School Board Approval:  April 16, 2024
Construction early start:  April 1, 2024
Last day of school:  June 14, 2024
Substantial completion:  October 18, 2024
Final Completion:  October 31, 2024
First day of school:  Sept 3, 2024