Franklin Middle School Auditorium Sound & Light System Upgrades
Franklin Middle School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.
Scope of Work
Franklin Middle School is scheduled to receive updates to their sound and light systems in the Auditorium.
Project Schedule*
Construction: TBD
Project Schedule*
Design: Fall/Winter 2023
Construction: June 2024
General Contractor: TBD
Architect: Schuler Shook
Substantial Completion: October 18, 2024
Bid Documents to be Issued: January 9, 2024
Mandatory Pre-bid Meeting: January 18, 2024
Bid Due Date: February 13, 2024
MPS Formal School Board Approval: April 16, 2024
Construction early start: April 1, 2024
Last day of school: June 14, 2024
Substantial completion: October 18, 2024
Final Completion: October 31, 2024
First day of school: Sept 3, 2024