Franklin MS Science Room Renovations

5

Franklin Middle School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Franklin Middle School is scheduled to receive updates to their existing science rooms including new flooring, sinks, countertops, exhaust fans, gas burners, plumbing, and ADA compliance.  

1501 Aldrich Ave. N
Minneapolis
MN
55411
612-668-2600

Project Updates

September- 

  • Project is completed

August- 

  • Project is scheduled to be substantially complete by August 16, 2024

June- 

  • Project is on track

May- 

  • Project is on track

April- 

  • Project is on track

March: 

  • Project is on schedule for June 17, 2024 start

December 2023: Project is in the submittal phase.  On schedule for June 2024 start.

October 2023: New Project

Contact Us

Ann Cerney, Project Manager

Phone: 612-685-3048

Email: Ann.Cerney@mpls.k12.mn.us

 

 

Project Schedule*

Design: Summer/Fall 2023

Construction: June 2024

General Contractor: Morcon Construction

Architect:  Wold Architects and Engineers

Substantial Completion: August 2024

CD Issue: 10/2/2023

Pre-Bid Meeting: 10/18/2023

Bid-Opening: 10/31/2023