FY25 Sitework

Scope of Work

Attached please find site plans for each project with the work planned for each school location.

Schedule:

MPS Board Approval:                     April 15, 2025 HARD DATE

Pre-Construction Meeting:        late April 2025

Last day of school:                         June 6, 2025

Last day for staff:                             June 10, 2025

Construction start:                         June 11, 2025

JUNETEENTH                                     June 19, 2025 – ALL MPS BUILDINGS CLOSED

Substantial Completion               August 15, 2025

Teachers & Staff back in Buildings week of August 18, 2025

Final Completion                             September 1, 2025

First day of school                          Sept 2, 2025

Resource

Contact Us

Ann Cerney, Project Manager

Phone: 612-685-3048

Email: Ann.Cerney@mpls.k12.mn.us

 

 

Consultant - Bolton + Menk

1601 Aldrich Ave. N
Minneapolis
MN
55411
612-668-2650
4315 31st Ave. S
Minneapolis
MN
55406
612-668-4520
3524 42nd Ave. S
Minneapolis
MN
55406
612-668-4900
5821 Wentworth Ave. S
Minneapolis
MN
55419
612-668-3370
5209 30th Ave. S
Minneapolis
MN
55417
612-668-4670
3131 19th Ave. S
Minneapolis
MN
55407
612-668-4300