FY25 Sitework
Scope of Work
Attached please find site plans for each project with the work planned for each school location.
Schedule:
MPS Board Approval: April 15, 2025 HARD DATE
Pre-Construction Meeting: late April 2025
Last day of school: June 6, 2025
Last day for staff: June 10, 2025
Construction start: June 11, 2025
JUNETEENTH June 19, 2025 – ALL MPS BUILDINGS CLOSED
Substantial Completion August 15, 2025
Teachers & Staff back in Buildings week of August 18, 2025
Final Completion September 1, 2025
First day of school Sept 2, 2025
Resource
FY25 Site Work - Multiple Locations
Consultant - Bolton + Menk
1601 Aldrich Ave. N
Minneapolis
MN
55411
612-668-2650
4315 31st Ave. S
Minneapolis
MN
55406
612-668-4520
3524 42nd Ave. S
Minneapolis
MN
55406
612-668-4900
5821 Wentworth Ave. S
Minneapolis
MN
55419
612-668-3370
5209 30th Ave. S
Minneapolis
MN
55417
612-668-4670
3131 19th Ave. S
Minneapolis
MN
55407
612-668-4300