Heritage Gym Renovations

Heritage High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Work includes removal of existing floors and installing new athletic floors.  Renovations include asbestos abatement, removal of old wooden partitional doors, installation of new divider curtains, installation of new scoreboards and shot clocks.

Project Updates

April: 

  • Project has been completed.

March:

  • New Project

Schedule:

Remove existing wood folding partition in Heritage Gym

  • 3/25/24 – 3/28/24

Cut down existing HM doors in Heritage Gym

  • 3/25/24 – 3/28/24

Abatement of Existing Gym Floor in Heritage Gym

  • 3/29/24 – 4/12/24 (2 weeks)

Install new athletic floor at Metro Gym

  • 4/8/24 – 4/12/24 (1 week)

Paint lines on Metro Gym floor

  • 4/15/24 – 4/19/24 (1 week)

Install new athletic floor at Heritage Gym

  • 4/15/24 – 4/19/24 (1 week)

Paint dry time – No Traffic on Metro Gym Floor

  • 4/20/24 – 4/23/24 (4 days)

Paint lines on Heritage Gym floor

  • 4/22/24 – 4/26/24 (1 week)

Paint dry time – No Traffic on Metro Gym Floor

  • 4/27/24 – 4/30/24 (4 days)

Install new scoreboards & shot-clocks

  • After May 1st (pending shipment from factory)