Heritage High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Small addition and enhancement of the Laura Ingalls Wilder Complex to accommodate new safe & welcoming entrance on SW corner of building at Door #1.  This project also includes the filling of the exterior sunken courtyard to help make a safer and accessible entrance for all students and visitors to any of the 9 programs at the Wilder Complex.

Project Updates

January-

More information coming soon.

Contact Us

Ann Cerney, Project Manager

Phone: 612-685-3048

Email: Ann.Cerney@mpls.k12.mn.us

 

 

Project Schedule*

BOE Design Contract Approval: 12/10/24

Schematic Design Completion: 12/15/24

Stakeholder, Steering Committee, QAQC Review: Late December 2024

Design Development Completion: 12/31/24

Cost Estimate #1: 12/31/24

Construction Documents: 1/15/25

Cost Estimate #2: 1/15/25

Stakeholder, Steering Committee, QAQC Review: Late January 2025

Bid Documents Issued: 2/14/25

Cost Estimate #3: 2/14/25

Pre-Bid Meeting: 2/25/25

Addendum #1 Issued: 3/4/25

Bid Due Date: 3/13/25

BOE Construction Contract Approval: 4/8/25 HARD DATE

Pre-Construction Activities: April 2025

Construction Start: April 2025

Construction Substantial Completion: 12/15/25

Construction Final Completion: 12/30/25

Warranty Period ends (one year): December 2026

Architect: ATS&R

Contractor: TBD