Heritage High School
Heritage High School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.
Scope of Work
Small addition and enhancement of the Laura Ingalls Wilder Complex to accommodate new safe & welcoming entrance on SW corner of building at Door #1. This project also includes the filling of the exterior sunken courtyard to help make a safer and accessible entrance for all students and visitors to any of the 9 programs at the Wilder Complex.
Project Schedule*
BOE Design Contract Approval: 12/10/24
Schematic Design Completion: 12/15/24
Stakeholder, Steering Committee, QAQC Review: Late December 2024
Design Development Completion: 12/31/24
Cost Estimate #1: 12/31/24
Construction Documents: 1/15/25
Cost Estimate #2: 1/15/25
Stakeholder, Steering Committee, QAQC Review: Late January 2025
Bid Documents Issued: 2/14/25
Cost Estimate #3: 2/14/25
Pre-Bid Meeting: 2/25/25
Addendum #1 Issued: 3/4/25
Bid Due Date: 3/13/25
BOE Construction Contract Approval: 4/8/25 HARD DATE
Pre-Construction Activities: April 2025
Construction Start: April 2025
Construction Substantial Completion: 12/15/25
Construction Final Completion: 12/30/25
Warranty Period ends (one year): December 2026
Architect: ATS&R
Contractor: TBD