Joint MPS and MPRB Fastpitch Softball
Scope of Work
Fastpitch Softball Facilities Improvements, in support of Minneapolis Public Schools’ Title IX compliance work and how to align the improvements with the Minneapolis Park and Recreation Board’s Diamond Sports Facility Study and park service area long range vision plans.
We are working with MPRB on the project - click on the link below for addition information: Softball (Fastpitch) Fields Improvements - Minneapolis Park & Recreation Board
Project Schedule*
|
BOE Design Contract Approval
|
September 2025 |
|
Schematic Design Completion
|
October 2025 |
|
Stakeholder Review, Steering Committee Review, QAQC Review
|
November 2025 |
|
Design Development Completion
|
November 2025 |
|
Construction Documents
|
January 2026 |
|
Stakeholder Review, Steering Committee Review, QAQC Review
|
December 2025 |
|
Bid Documents Issued
|
February 2026 |
|
BOE Construction Contract Approval
|
April 2026 |
|
Pre-Construction Activities |
April 2026 |