Justice Page Middle School Renovations

A colorful, geometric-patterned floor leads toward a wall with abstract art and a brightly lit ceiling in a modern hallway.

Justice Page Middle School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Capital renovations for the improvements to the lower level including the kitchen, cafeteria, gymnasium, and restrooms.  

1 West 49th St.
Minneapolis
MN
55419
612-668-4040

Project Updates

August -

Construction in progress

April-

Starting kitchen demolition May 18th.

March-

No new updates

February-

Began preconstruction including submittal review

January-

Versacon has been selected as the general contractor. The contract was approved Jan 13th in the last board meeting

Contact Us

Diedra Geye, Project Manager

Phone: 612-668-0055

Email: Diedra.Geye@mpls.k12.mn.us

Project Schedule*

Design: Miller Dunwiddie, Winter 2024/Spring 2025 

Bid Opening: November 6, 2025 

Construction: May 2026 

Substantial Completion: January 2027 

Final Completion: March 2027 

General Contractor: Versacon

Project Photos and Resources

Justice Page Middle School Reno

A colorful, geometric-patterned floor leads toward a wall with abstract art and a brightly lit ceiling in a modern hallway.
In the foreground, unfinished metal ductwork and framing are visible, while the background features a metallic wall with two doors and ventilation systems.
Tiled flooring fills the foreground of an unfinished commercial kitchen with stainless steel ventilation hoods and gray tiled walls in the background.
Two orange ladders stand in the foreground of a construction site with exposed ceilings and metal framing, while a worker in a yellow vest is visible in the background.
A white column stands in the foreground on a tiled floor, while the background reveals a room with metallic walls and industrial equipment.