Justice Page Middle School Renovations

Justice Page Middle School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.
Scope of Work
Capital renovations for the improvements to the lower level including the kitchen, cafeteria, gymnasium, and restrooms.
1 West 49th St.
Minneapolis
MN
55419
612-668-4040
Project Schedule*
Design: Miller Dunwiddie, Winter 2024/Spring 2025
Bid Opening: November 6, 2025
Construction: June 2026
Substantial Completion: July 2027
Final Completion: September 2027
General Contractor: TBD