Las Estrellas Dual Language Elementary School Welcoming Entrance
Las Estrellas Dual Language Elementary School is scheduled to undergo a significant renovation and is outlined below. To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.
Scope of Work
A new safe and welcoming entrance project to bring the school to current best practice for safety and visitor management. The entrance will include safety features, upgraded intercom and visitor check in station.
Project Schedule*
Design: To be completed January 2025
Construction:
General Contractor:
Architect: Wendel
Substantial Completion: August 2025
Bid Documents to be Issued: February 2025
MPS Formal School Board Approval: April 2025
Start exterior construction work: Mid-April 2025
Start interior construction renovations: June 2025
Construction Final Completion: October 2025