LED Lighting, Lighting Control, and Ceiling Improvements

Multisite Project - LED Lighting, Lighting Control, and Ceiling Improvements.

School Locations: 

  • Susan B Anthony Middle School
  • Olson Middle School
  • River Bend Education Center
  • Harrison Education Center

Scope of Work

Building wide replacement of fluorescent lighting with LED lighting fixtures and implementation of digital lighting controls. Limited ceiling work to replace ceilings and facilitate the lighting replacement.

Susan B. Anthony- Susan B. Anthony Middle School is scheduled to receive lighting upgrades, changing from fluorescent to LED light fixtures, adding lighting controls, and performing some ceiling improvements.

Olson Middle School- Olson Middle School is scheduled to receive lighting upgrades, changing from fluorescent to LED light fixtures, adding lighting controls, and performing some ceiling improvements. 

River Bend Education Center/Harrison Education Center - River Bend and Harrison are scheduled to receive lighting upgrades.  Existing fluorescent and incandescent fixtures will be upgraded to efficient LED lighting and lighting controls.

Project Updates

September 2023: 

Anthony/Olson lighting project

  • No additional updates at this time.

River Bend/Harrison

  • Project is complete

August 2023: 

Anthony/Olson lighting project

  • No additional updates at this time.

River Bend/Harrison

    • Lighting upgrades are done at Harrison
    • River Bend lighting is substantially complete.  Punch list items currently in process.
      1. Entry atrium specialty wall sconce fixtures are on order – installation will be scheduled when fixtures arrive

July 2023: 

Anthony/Olson lighting project

  • No additional updates at this time.

River Bend/Harrison

    • Lighting at Harrison Education Center is substantially complete.
    • Lighting at River Bend Education Center currently underway.  Installation to be completed by mid-August.


    •  

June 2023: 

Anthony/Olson lighting project

  • No additional updates at this time.

River Bend/Harrison

    • Harrison Lighting
      1. Lighting installation is almost complete.
      2. Lighting controls installation in process.
    • River Bend Lighting
      1. Work begins June 20th


    •  

May 2023: 

Anthony/Olson lighting project - 

  • No additional updates at this time.

River Bend/Harrison

    • Olson Middle School -Llighting project is complete.
    • Anthony Middle School – Lighting project is complete.
    • Construction commenced May 1, 2023

April 2023: Currently there are no updates for Anthony/Olson and River Bend/Harrison lighting 

March 2023: 

Anthony/Olson lighting project

  • Olson Middle School - lighting project is substantially complete.
  • Anthony Middle School – Lighting and controls to be substantially completed March.

River Bend/Harrison

  • No additional updates at this time.

January 2023: Currently there are no updates for Anthony/Olson and River Bend/Harrison lighting

December 2022: 

Anthony/Olson lighting project

  • Steady progress continues in upgrading classroom, office, and corridor lighting throughout Anthony Middle School.  Delivery lead time for select digital lighting controls and minor fixture revisions will extend project completion to mid-February.
  • Lighting upgrades are progressing daily at Olson Middle School.  Project completion is projected for mid to late January.

River Bend/Harrison-

  • Sheehy Construction has been awarded the River Bend and Harrison Lighting Upgrades project.
  • Board approval of contract December 13, 2022
  • Work Commences May 1, 2023

 

November 2022: 

River Bend/Harrison-

  • Bids have been opened.  In the process of confirming the low bidder and preparing the contract for the December MPS Board meeting.

Anthony/Olson lighting project

  • Upgrading outdated light fixtures to energy efficient lighting is underway.  Outdated fluorescent and incandescent fixtures are being replaced with new LED fixtures and lighting controls.

October 2022: 

River Bend/Harrison-

  • Receive bids November 3, 2022

  • Board Award January 2023

  • Work commences May 1, 2023

  • Substantial completion August 2023

Northeast- No updates to report

Anthony/Olson lighting project

  • Contractor – NAC Mechanical and Electrical Services

  • Work commences October 17, 2022

  • Substantial completion December 2022

September 2022: Project is on schedule for all three schools.

August 2022: 

Anthony/Olson lighting project

  • Contract to August Board consent agenda.
  • Tentative construction start – October 2022
  • Tentative project completion – December 2022

July 2022: 

  • Bids opened -  NAC Mechanical and Electrical Services awarded as project contractor.
  • August MPS Board meeting for contract approval

June 2022: Project in bidding – bids to be opened on June 28, 2022.

May 2022: Project is currently on track and there are no updates to report at this time.

April 2022: The project has started the design process.

Contact Us

Don Bielinski, Jr., Project Manager

Phone: 612-668-0700

Email: Donald.Bielinskijr@mpls.k12.mn.us

 

Project Schedule*

Design: Spring 2022

Construction Start: October 2022

Substantial Completion: December 2022

Architect: ATS&R 

General Contractor: TBD

 