Multi-Site Flooring Upgrades
Scope of Work
Flooring replacement or wood floor refinishing at Jenny Lind, Kenny, Nellie Stone Johnson, Lucy Craft Laney, Ella Baker, Hale, and Waite Park.
Ella Baker:
- Work
Hale:
- Work
Jenny Lind:
- Work
Kenny
- Work
Nellie Stone Johnson:
- Work
Lucy Craft Laney:
- Work
Waite Park:
- Work
Contact List
Kanjana Foster, Project Manager
Phone: 612-668-0382
Project Schedule*
Design: Winter 2026
Consultant: Miller Dunwiddie
General Contractor: TBD
Substantial Completion: August 2026
Bidding: Spring 2026
Construction start: June 2026
Substantial completion: August 2026
Final Completion: September 2026