Multi-Site Summer Boilers

Scope of WorkAdd condensing boilers to increase energy conservation, utility savings, and improved heating controls at multiple sites.  The sites included in this program are Andersen, Green Central, Jenny Lind, Pillsbury and Sullivan.  MPS will also receive rebates from CenterPoint Energy for this energy conservation effort.

Andersen:  

  • Work

Green Central

  • Work

Jenny Lind:

  • Work 

Pillsbury:

  • Work 

Sullivan:  

  • Work

 

Project Updates

February-

On schedule and on budget

Contact List

Grant Lindberg, Project Manager

Phone: 612-668-0281

Email: Grant.Lindberg@mpls.k12.mn.us

 

Project Schedule:  Summer 2026

Design:  Complete

Consultant: Wold

General Contractor: Davis Mechanical

Architect:  Wold

Substantial Completion: August 2026

Bid Documents to be Issued:  December 2026

Mandatory Pre-bid Meeting: January 2026

Bid Due Date:  January 2026

MPS Formal School Board Approval:  February 10, 2026 

Construction early start: June 2026

Last day of school: June 2026 TBD

Substantial completion: August 2026

Final Completion:   August 2026

First day of school:   August 2026