Multi-Site Summer Boilers
Scope of WorkAdd condensing boilers to increase energy conservation, utility savings, and improved heating controls at multiple sites. The sites included in this program are Andersen, Green Central, Jenny Lind, Pillsbury and Sullivan. MPS will also receive rebates from CenterPoint Energy for this energy conservation effort.
Andersen:
- Work
Green Central:
- Work
Jenny Lind:
- Work
Pillsbury:
- Work
Sullivan:
- Work
Contact List
Grant Lindberg, Project Manager
Phone: 612-668-0281
Email: Grant.Lindberg@mpls.k12.mn.us
Project Schedule: Summer 2026
Design: Complete
Consultant: Wold
General Contractor: Davis Mechanical
Architect: Wold
Substantial Completion: August 2026
Bid Documents to be Issued: December 2026
Mandatory Pre-bid Meeting: January 2026
Bid Due Date: January 2026
MPS Formal School Board Approval: February 10, 2026
Construction early start: June 2026
Last day of school: June 2026 TBD
Substantial completion: August 2026
Final Completion: August 2026
First day of school: August 2026