Skip To Main Content

Select a School

North High School Cooling

28

 

North High School is scheduled to undergo a renovation. The project scope is outlined below. To receive periodic updates on project milestones, community meeting invites and other news, please sign up to receive e-alerts.

1500 James Ave. N
Minneapolis
MN
55411
612-668-1700

Scope of Work

Continued improvements to North High School including classroom renovations and new cooling systems. 

Project Updates

February 2023: The North CTE project is being completed quickly by the Contractor. The Dance Studio and Weight Room are scheduled to be completed by Spring Break. Once completed, the weight equipment, currently in the Auxiliary Gym, will be relocated to the new weight room. With the Auxiliary Gym empty, demolition of the gym will begin. A new auxiliary gym will be constructed that will also serve as a storm shelter. The new auxiliary gym construction is expected to take about 12 months to complete.

The second floor of the new CTE center is going through some finish work. Installation of the Unistrut is underway which will provide overhead power and data for the CTE rooms. Door frames are being built and when installed, flooring can be installed. The single user restrooms on the second floor are also under construction.

The first floor CTE construction is focusing on the moveable wall installation and mechanical and electrical installations. The project is on schedule to be available for instruction in Fall 2023.

The utility tunnel construction has been completed and installation of heating and cooling pipes is underway. The solar array connection is being redesigned and scheduled to be installed in March.

The Phase 2 contract has been award to Rochon and they will begin construction in April with the installation of the new sewer pipeline that will be installed under the west and south parking lot areas. The Phase 2 project will include the new grand entrance and the entry commons and dining area.

Contact Us

Curt Hartog
Executive Director, Capital Planning, Construction, Maintenance and Operations
612-668-0274
curtis.hartog@mpls.k12.mn.us

Project Schedule*

Design: 

Pre-Construction: 

Construction: 

Substantial Completion: 

Final Completion: 

General Contractor: 

Image

North High School Cooling