Skip To Main Content

Select a School

Roosevelt High School Career & Technical Education Improvements

A person walks on a sidewalk in front of a modern brick building with large garage doors, set against a backdrop of trees and a blue sky with clouds.

Roosevelt High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

4029 28th Ave. S
Minneapolis
MN
55406
612-668-4800

Scope of Work

Renovations and expansion of the Career & Technical Education Center (CTE). Phase 1 included interior renovations to the construction and collision labs. Phase 2 includes an expansion of the auto shop, a new entrance, classrooms, welding, machine and small engines spaces.

Project Updates

November-

Renovation of interior spaces in progress. New welding lab to be delivered by Winter Break 2026. New addition for auto shop and CTE entrance under construction. Parking lot curbs underway.

October-

Click here to see the latest LSE's Field Observation Report

September-

Click here to see the latest LSE's Field Observation Report

August-

Click here to see the latest LSE’s Field Observation Report

July-

Preconstruction meeting held on July 8th, 2026.

Security fence installed. Interior demolition has started. Northeast parking lot has been striped. Excavation for footings for building addition to begin shortly.

June-

The Board of Education approved Rochon Corporation’s construction contract for Phase 2 on June 9th, 2026.

May-

Bid opening for Phase 2 held on May 14th, 2026. LSE Architects recommends award of contract to Rochon Corporation contingent on Board of Education approval.

April-

Revised Phase 2 documents posted for bids on April 14th, 2026 (OP#26-2623)

Mandatory pre-bid meeting held on April 29th, 2026.

March-

Construction Results Corporation finalizing the installing of the construction lab dust collector sweeps and controls for Phase 1.

February-

Phase 1 owner trainings and close-out documents in progress.

January-

Substantial Completion signed January 16, 2026  for Phase 1 delayed work (Overhead door 1024B in Collision, dust collector system, completion of secure entry items, electrical punchlist items, mechanical insulation and identification, TAB and commissioning items).

December-

Click here to see the latest LSE Field Observation Report

Bid opening for Phase 2 held on December 16, 2026. No contract awarded as all bids received were over project budget. Revision of Phase 2 schedule and phasing underway.

November-

Click here to see the latest LSE Field Observation Report

October-

Click here to see the latest LSE’s Field Observation Reports

September-

  • CRC is doing Punchlist completion
  • Dust collector work to occur over MEA
    • Structural Steel

July-

  • Substantial Completion on 15Aug25
  • See attached LSE/Hallberg Field Observation Reports.

May-

  • Pre-Construction Conference set for 27May25.
  • CRC (Construction Results Corporation) set to Mobilize & Begin on 11Jun25.
  • Moving/Abatement to be coordinated with CRC.

April-

  • Construction Results won’t begin until around 12Jun25
  • We are in the pre-construction phase.  Submittals and etc., prior to construction.

March-

  • Construction Results
    • Contract start up
    • Submittals

February -

  • In Contract award phase.
  • Construction Results submitting “Notice of Award” and “Notice to Proceed” submittals.
  • Pre-Construction Conference to occur sometime in April or May.

January -

  • Awarded in BOE meeting. CTE Phase I:  Construction Results Corp

Contact Us

Julia Kastelberger, Project Manager

Phone: 612-461-3732

Email: julia.kastelberger@mpls.k12.mn.us

Project Schedule*

Design: LSE Architects

Phase 1:

Construction: June 14th, 2025 to January 16th, 2026

General Contractor:  Construction Results Corporation

Bid Documents Issued:  November 14th 2024

Mandatory Pre-bid Meeting:  November 27th 2024

Bid Due Date:  December 10th 2024

MPS Formal School Board Approval:  January 14th 2026

Substantial Completion: January 16th, 2026

Final Completion: August 2026

Phase 2:

General Contractor:  Rochon Corporation

Bid Documents Issued:  April 14th, 2026

Mandatory Pre-bid Meeting:  April 29th, 2026

Bid Due Date:  May 14th, 2026

MPS Formal School Board Approval:  June 9th, 2026

Last day of school:  June 10th, 2026

Construction Start: July 20th, 2026

First day of school:  September 8th, 2026

Substantial Completion:  August 10th, 2027

Final Completion:  September 24th, 2027

Project Photos and Resources

Roosevelt High School Renovations

Two large silver ventilation pipes run along a red brick wall in the foreground against a pale, overcast sky and another brick building in the background.
A worker stands on a metal platform in the foreground, wiring an electrical box mounted against a red brick wall in the background.
A grey electrical control panel with buttons and a warning sign is mounted on a plywood wall against a concrete background.
A large silver ventilation pipe runs along the top of a red brick building under a cloudy grey sky.
Industrial machinery and a red ladder sit on a snow-covered platform in front of a brick building.
A snow-covered industrial dust collection system with a ladder and a worker stands on a metal platform in front of a brick building.
A snow-covered ground sits in the foreground beneath a metal platform with a grated surface and equipment in the background.
A snow-covered metal grate platform sits atop a galvanized steel base in a snowy outdoor setting with a brick wall in the background.
A worker stands on a metal platform next to a large grey industrial ventilation unit installed against a brick building in a snowy alley.
A large, open industrial workspace with concrete floors, exposed ceiling beams, and various equipment and workstations scattered throughout the space.
A large industrial workspace with various equipment, tools, and storage areas visible throughout the space.
A well-equipped auto repair shop with various tools and equipment, including a van with its hood open, indicating ongoing maintenance or repair work.
A spacious classroom with wooden tables, stools, and a large screen display on the wall, suggesting an educational or training environment.
A person walks on a sidewalk in front of a modern brick building with large garage doors, set against a backdrop of trees and a blue sky with clouds.