South High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

3131 19th Ave. S
Minneapolis
MN
55407
612-668-4300

Scope of Work

A new safe and welcoming entrance that includes new administrative offices and upgraded entrance features for safety and visitor controls. 

Relocation of entrance and front office to the original entrance location on 19th Avenue South. The goal is to create a welcoming and inclusive space that fosters a sense of belonging and enhances the entry experience while improving student safety.

The project will include clear wayfinding, strategic visibility, and exterior improvement to improve the entry experience. 

Project Updates

July-

Substantial Completion was delayed until August 18th with the exterior metal panel coming mid to late September

May-

Construction is underway with a substantial completion date of August 6th.

January-

Jorgenson Construction, Inc (JCI) was selected as general contractor.

August-

Cuningham Group presented design perspectives for MPS approval. Images are shown below

February-

Construction starting early 2026

 

Contact Us

Mauricio Ochoa, Project Manager

Phone: 612-559-2574

Email: Mauricio.Ochoa@mpls.k12.mn.us

 

 

Project Schedule*

Design: Cuningham Group

General Contractor: Jorgenson Construction, Inc

Bid Documents to be Issued: October 17, 2025

Bids Due: November 25, 2025

Board Approval: January 13, 2026

Construction Start: February 1, 2026

Substantial Completion: August 18, 2026