Skip To Main Content

Select a School

South High School Safe and Welcoming Project

SOUTH

South High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

3131 19th Ave. S
Minneapolis
MN
55407
612-668-4300

Scope of Work

A new safe and welcoming entrance that includes new administrative offices and upgraded entrance features for safety and visitor controls. 

Relocation of entrance and front office to the original entrance location on 19th Avenue South. The goal is to create a welcoming and inclusive space that fosters a sense of belonging and enhances the entry experience while improving student safety.

The project will include clear wayfinding, strategic visibility, and exterior improvement to improve the entry experience. This project also includes the creation of single user bathrooms and improvements to the health office. 

Project Updates

August-

Cuningham Group presented design perspectives for MPS approval. Images are shown below

February-

Construction starting early 2026

 

Contact Us

Mauricio Ochoa, Project Manager

Phone: 612-559-2574

Email: Mauricio.Ochoa@mpls.k12.mn.us

 

 

Project Schedule*

Design: Cuningham Group

General Contractor: TBD

Bid Documents to be Issued: October 17, 2025

Bids Due: November 25, 2025

Board Approval: January 13, 2026

Construction Start: February 1, 2026

Substantial Completion: August 1, 2026

Project Photos and Resources

South High School

SOUTH
South
South