Southwest High School HVAC & LED Upgrades, Phases 1 - 5

Southwest High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Kraus-Anderson Construction Company has been selected as an Agency Construction Manager by Minneapolis Public Schools to administer the construction project for Southwest High School HVAC & LED lighting upgrades.  The overall project consists of HVAC upgrades, including new Chillers for adding air conditioning system to high school and new air handling units.  Also includes LED lighting upgrades, new electric voltage regulator, roof replacements, and related interior modifications.

Work in Areas A & B to begin June 2026. 

Work in Areas C, D, E, F, and attic space to begin June 2027.

Phase 1 & 2 Bid Packages were bid out on October 7, 2025, and approved by MPS Board on February 10, 2026.

Phases 3, 4, & 5 to be bid out at a later date tbd.

Work Updates

The following is an update on construction activities that will be taking place this summer on campus:

Work Updates 

October-

Work in Areas A & B completed September 2026. 

April-

We are embarking on a large-scale roof replacement and HVAC upgrade project that will be phased out over the next several summers/years.

Summer 2026, we focused on the Eastern wing along 47th and Abbot Ave S.

2027 Project Plans

Phase 2 will start Spring 2027.

You can expect to see increased construction traffic Mon-Friday 7am-5pm.

There will be several cranes, delivery trucks, and other construction vehicles around site throughout the duration of the project.

We will need to remove portions of our existing roof in sections, replace that area with a built-up roof and temporarily seal each section every night.

The demolition process will likely generate some dust. Rest assured, the existing roof was tested and confirmed to have no ACM. 

This will likely be the noisiest part of each day.

There will be a kettle on site that will heat the new asphalt (tar) for application. This will generate a noticeable amount of odor. While this odor may not be pleasant and will vary depending on which way the wind is blowing each day, it is not toxic and will not cause harm to anyone exposed to it.

We appreciate your patience and understanding as we work to complete these important updates for our campus.

2026 Project Plans

We are embarking on a large-scale roof replacement and HVAC upgrade project that will be phased out over the next several summers/years.

This summer 2026, we will be focusing on the Eastern wing along 47th and Abbot Ave S.

You can expect to see increased construction traffic Mon-Friday 7am-5pm.

There will be several cranes, delivery trucks, and other construction vehicles around site throughout the duration of the project.

We will need to remove portions of our existing roof in sections, replace that area with a built-up roof and temporarily seal each section every night.

The demolition process will likely generate some dust. Rest assured, the existing roof was tested and confirmed to have no ACM. 

This will likely be the noisiest part of each day.

There will be a kettle on site that will heat the new asphalt (tar) for application. This will generate a noticeable amount of odor. While this odor may not be pleasant and will vary depending on which way the wind is blowing each day, it is not toxic and will not cause harm to anyone exposed to it.

We appreciate your patience and understanding as we work to complete these important updates for our campus.

3414 West 47th Street
Minneapolis
MN
55410
612-668-3030

Contact Us

Ann Cerney, Project Manager

Phone: 612-685-3048

Email: Ann.Cerney@mpls.k12.mn.us

Updates

If you would like to receive updates about this project, please share your name and email by clicking the button below.

Submit Information

Project Schedule*

Design: Completed 1/1/2025

Construction: Starting 4/20/26

Construction Manager: Kraus-Anderson

Architect:  ATS&R Architects & Engineers

Construction Final Completion:  2030           

Resource

Project Updates

October-

Phase 1 has been completed.

July-

New pumphouse and chiller #1 has been craned onto the upgraded roof area.  See attached photos.

Roof replacement work is behind schedule due to the heavy rains in June, then dangerously high temperatures in July.  At one point, the temperature on the roof reached 160 degrees.  Crews are working overtime to complete the work prior to the start of school on September 8th.   Interior lighting upgrades are going well and expected to be done on time.

June-

Project is gearing up for summer construction crunch with last day of school being June 10th.  Working hours will be Monday-Friday, 7am – 6pm.  There will be no work on June 19th in respect of Juneteenth.  Removal of old roof has started and removal of old mechanical equipment to follow.  Crane pick for chiller and pump house scheduled tentatively for the first week of July.  Structural support work for new roof equipment is on schedule.  Interior LED lighting upgrades scheduled to begin week of June 15th.

April-

Preconstruction work and mobilization is in process for Phase 1.  New chiller, pumps, and pumphouse are on track to be delivered to jobsite May 2026.  Roofing demolition in Areas A, B, & C scheduled to being June 2026.  Items to be completed over the summer 2026 include installing steel structural support to support roof weight of new chiller and pumphouse.  New rooftop stair will be installed to new pumphouse.  Selective removal and replacement of new LED light fixtures to be completed in east building.  Air handling units will be upgraded. 

Phase 2 work scheduled to begin Spring 2027.  Work has been bid out as separate bid packages, and contractors have been selected and awarded contracts.  Work packages include demolition, concrete, masonry, landscaping, structural steel, roofing, carpentry, sheetmetal, drywall, acoustical ceilings, painting, fire suppression, controls, building automation, mechanical, plumbing, testing & balancing, electrical, and commissioning.

March-

Project is on schedule

Project Photos and Resources

In the foreground, rows of colorful solar panels are being installed on a rooftop, while in the background, HVAC units and a red-trimmed building are visible under a cloudy sky.
Workers are busy on a construction site with large pipes and equipment in the foreground, while a lush green forest and houses form the background.
A large crane hoists equipment onto a rooftop with solar panels in the foreground, while a building and trees are visible in the background under a cloudy sky.
Scaffolding in the foreground overlooks a construction site with stacks of materials and trees in the background.
Colorful solar panels are arranged on a rooftop in the foreground, with buildings and a cloudy sky in the background.
A large red and white crane lifts a rectangular object in the foreground, with a modern brick building and cloudy sky in the background.
Insulated white pipes run along a black rooftop between a grey industrial unit and a red structure under a cloudy sky.
Insulated white pipes run across a black rooftop in the foreground, set against a large red building and a cloudy sky in the background.
White insulated pipes run across a dark rooftop in the foreground, with a large red building wall and a cloudy sky in the background.
Pink and blue solar panels sit in the foreground of a rooftop featuring industrial HVAC units and a red wall under a cloudy sky.