Southwest High School HVAC & LED Upgrades, Phase 1 - 5

Southwest High School is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Kraus-Anderson Construction Company has been selected as an Agency Construction Manager by Minneapolis Public Schools to administer the construction project for Southwest High School HVAC & LED lighting upgrades.  The overall project consists of HVAC upgrades, including new Chillers for adding air conditioning system to high school and new air handling units.  Also includes LED lighting upgrades, new electric voltage regulator, roof replacements, and related interior modifications.

Work in Areas A & B to begin June 2026. 

Work in Areas C, D, E, F, and attic space to begin June 2027.

Phase 1 & 2 Bid Packages were bid out on October 7, 2025, and approved by MPS Board on February 10, 2026.

Phases 3, 4, & 5 to be bid out at a later date tbd.

3414 West 47th Street
Minneapolis
MN
55410
612-668-3030

Project Updates

March-

Project is on schedule

Contact Us

Ann Cerney, Project Manager

Phone: 612-685-3048

Email: Ann.Cerney@mpls.k12.mn.us

 

 

Project Schedule*

Design: Completed 1/1/2025

Construction: Starting 4/20/26

General Contractor: Kraus-Anderson

Architect:  ATS&R Architects & Engineers

Construction Final Completion:  2030           