Scope of Work
Roof repair over gym area.
Project Schedule*
Architect: Inspec, Inc.
General Contractor: Central Roofing
School Board Approval: April 15, 2025
Construction start date: June 9, 2025
Substantial completion date: August 15, 2025
Final Completion date: August 29, 2025