Scope of Work

Roof repair over gym area.

 

Project Updates

April- 

Construction start date: June 9, 2025 

October-

  • More about this project coming soon

Contact Us

Diedra Geye, Project Manager

Phone: 612-668-0055

Email: Diedra.Geye@mpls.k12.mn.us

Project Schedule*

Architect:  Inspec, Inc.

General Contractor: Central Roofing

School Board Approval: April 15, 2025  

Construction start date: June 9, 2025  

Substantial completion date:   August 15, 2025

Final Completion date:  August 29, 2025