Multi-Site Locker Room Renovations

 

Scope of Work

Title IX is a federal law that prohibits sex-based discrimination in any educational program or activity that receives federal funding.  The law protects both students and employees from sex-based discrimination. Title IX has specific provisions for athletic programs, covering areas like participation opportunities, athletic scholarships, and other items such as equal space for male and female locker rooms.  Title IX regulations require "comparable facilities".  Title IX requires that if separate facilities like locker rooms are provided, they must be comparable for students of one sex to those provided for the other. 

MPS Stakeholders including Athletic Directors and Principals are working together to modify existing locker room facilities to create equal spaces for both males and females.

 

Current Project Sites

  • Camden Locker Rooms
    • Design work is starting with the goal of work being completed summer 2026.
    • Locker Rooms will be modified Summer 2026.

 

  • Edison Locker Rooms
    • Work is complete

 

  • North HS Locker Rooms
    • Design in process for tentative 2027 summer construction

 

  • Roosevelt Locker Rooms
    • Work is complete

 

  • South Locker Rooms
    • Design in process for tentative 2027 summer construction

 

  • Southwest Locker Rooms
    • ​​​​​​​Work Completed

 

  • Washburn Locker Rooms
    • Design work is starting with the goal of work being completed summer 2026.
    • Locker Rooms will be modified Summer 2026.

 

Project Updates

2026

June-

Construction contract has been awarded to Dering Pierson Group.  Work is on schedule to being week of June 15, 2026 at both Camden HS and Washburn HS.

April- 

Title IX renovations in the locker rooms at Camden H.S. and Washburn H.S. are scheduled to begin June 2026.  Work was bid out and contract awarded to general contractor, Dering Pierson Group.  Renovations include creating new storage rooms at both Camden H.S. and Washburn H.S. and modifying boys locker room to match size of existing girls locker room.   Washburn H.S. also includes updating corridor between boys locker room and weight room to be fire-rated egress hallway per building and fire codes.  Work is scheduled to be substantially complete by September 1, 2026.

Images

There are no resources or collections to display

Contact List

Ann Cerney, Project Manager

Phone: 612-668-0013

Email: Ann.Cerney@mpls.k12.mn.us

Project Schedule:Bid Phase: February 2026

MPS Board Approval:  April 2026

Construction Start:  June 2026

Substantial Completion:  September 1, 2026

Project Team:

Antony Fisher, CMAA, District Director of Athletics

Dan Goemann, District Master Planner

Brett McNeal, CMAA, Director of Athletics, Camden HS

Dr. Kiristen Robinson, CMAA, Director of Athletics, Edison HS

Kale Severson, Director of Athletics, North HS

Adam Flanders, CAA, Director of Athletics, Roosevelt HS

Amy Cardarelle, Director of Athletics, South HS

Jared Mountain, Director of Athletics, Southwest HS

Giovan Jenkins, CAA, Director of Athletics, Washburn HS

Ann Cerney, Facilities Project Manager

Wold Architects, Design Team

Locker Room Updates