Transportation Center Fire Protection Sprinkler System Upgrade

Transportation Center is scheduled to undergo a significant renovation and is outlined below.  To receive periodic updates on project milestones and other news, please sign up to receive E-alerts.

Scope of Work

Upgrade fire sprinkler system in the MPS Transportation Bus Garage.

Project Updates

December

  • Project is finished

November -

  • Construction being completed on upgrade to the fire sprinkler system in the bus garage.  Work is substantially complete.

October -

  • No new updates.

September-

  • Fire Sprinkler system upgrade work is underway in the Transportation bus garage.  Completion – November 2024.

August-

  • Replacement of the fire sprinkler system in the MPS Transportation bus garage began August 5th. Substantial completion of work is scheduled for mid-November.

July-

  • Fire Sprinkler pre-construction meeting on July 17th
  • Sprinkler replacement in the bus garage to begin August

June-

  • Contract on June 11th Board Consent Agenda.

May-

  • Contractor – Dynamic Fire Protection
  • Construction schedule: August 2024 – November 2024

April-

  • In bidding – bids due April 18, 2024

March-

  • 95% bid documents have been completed.
  • Project to advertise Mid- March 2024.
  • Bids opened April 18, 2024.
  • Construction summer/fall 2024

February -

  • Project to start in Summer/Fall 2024

Contact Us

Don Bielinski, Jr., Project Manager

Phone: 612-668-0700

Email: Donald.Bielinskijr@mpls.k12.mn.us

 

Project Schedule*

Design Consultant: KFI Engineers
Bid Opening: Spring 2024
Construction Start: Summer/Fall 2024